The South Addition and South Entrance officially opened on August 26, 2024 and it has been so exciting to see members and families using the new spaces. From Nursery School Continue Reading »
We are excited to announce that starting Monday, August 26, the South Addition and South Entrance will officially be open for use! Over the summer weeks, construction crews have been Continue Reading »
Several exciting milestones have been reached since our last update in early May! First, Temple Sinai has passed all of the inspections to receive a Temporary Certificate of Occupancy for Continue Reading »
A lot has happened over the past few weeks as our construction team has taken advantage of our schools’ Spring and Passover Breaks! The exterior plating of the awning covering Continue Reading »
It’s springtime at Temple Sinai and the cherry trees planted in the fall are now blooming! For those who have driven to the temple this past week, you have probably Continue Reading »
The upper level of the South Addition is in great shape with only a few installation pieces remaining, including A/V and some glass railing. While the doors to the South Continue Reading »
Major work has started on the exterior of the South Addition over the past couple of weeks! Concrete has been poured for the new South Entrance stairs and covered entryway. Continue Reading »
Over the past couple of weeks, significant work has been done to install the new doors in the South Addition—in particular the new secure school wing doors. Additional layers of Continue Reading »
While the holidays are a time for rest and relaxation for many, the South Addition construction continues at full speed! In the past couple of weeks, the hardwood flooring and Continue Reading »
The South Addition is getting closer and closer to completion! The South Entrance glasswork, called “the storefront” in construction terms, has been installed along with the other windows. Additionally, lighting Continue Reading »